Public Works Plumbing Subcontractor v. General Contractor and Payment Bond Surety

The firm represented a plumbing subcontractor to pursue claims for the unpaid subcontract balance plus delay and disruption for work performed at a publicly funded construction project.  After filing suit against the general contractor and its payment bond surety, the firm obtained public records demonstrating the general contractor was paid for the work of the subcontractor, but had not paid the subcontractor.

Public records leveraged in negotiating six-figure settlement.

The firm used the public records to negotiate a six-figure settlement where the general contractor paid the subcontractor all amounts due, prompt-payment penalties of two percent per month, as well as all attorneys’ fees and costs incurred to pursue payment.