Skip to content

General Contractor v. Subcontractor

The firm successfully brought a lawsuit by a general contractor against a subcontractor. The subcontractor quit work on a construction project because of a dispute over payment and scope with the general contractor. The general contractor’s lawsuit sought damages for delays to the project and extra costs to supplement the subcontractor’s work. The subcontractor brought a cross-complaint against the general contractor for alleged damages resulting from a payment dispute on a separate construction project. Because of the firm’s knowledge of construction delays and project requirements, the firm successfully negotiated a settlement with the subcontractor with the general contractor receiving installment payments of least $300,000. Additionally, the subcontractor agreed to dismiss its cross-complaint with prejudice with no liability or amount owed by the firm’s client or surety.

Counsel: Jeffrey B. Baird and Daniel P. Scholz

Back To Top