The firm’s client requested substitution of a listed subcontractor based on its failure to prosecute its work in a timely manner. The subcontractor’s failure to advance the work was delaying the project’s completion. The subcontractor opposed substitution contending it had not been paid for work performed. Following a contested evidentiary hearing, the college’s appointed hearing officer granted the substitution.
Counsel: Jason R. Thornton