SUCCESSFUL BID PROTEST, PUBLIC WORK OF IMPROVEMENT CONTRACT
The firm’s client was the second-low bidder on a public works contract for the City of Pomona. However, the low…
The firm’s client was the second-low bidder on a public works contract for the City of Pomona. However, the low…
The firm represented the general contractor on an airport improvement project. A surveyor was overheard referring to a project engineer…
The firm represented a design-build contractor in arbitration related to cost overruns and delays caused by the state’s failure to…
The firm represented a general contractor bridge builder against a specialty design-build subcontractor in a lawsuit. Both parties alleged material…
The firm represented a general contractor in pursuing a plumbing subcontractor and its performance bond surety for the cost to…
The firm represented a real estate investor who had purchased property on behalf of a joint venture, putting his partner…
The firm represented a framing subcontractor pursuing its outstanding subcontract balance which had been paid to the general contractor by…
The firm obtained a rapid recovery for a financier client on a past-due note secured by multiple properties. The firm's…
Hundreds of design changes cause 15-month construction delay. The firm represented the general contractor in its pursuit of its contract…