RECOVERY OF DELAY AND DISRUPTION BASED ON DIFFERING SITE CONDITIONS
The firm represented the prime contractor and one of its subcontractors against a Port District on a claim for extra…
The firm represented the prime contractor and one of its subcontractors against a Port District on a claim for extra…
The firm successfully represented a client which was the lowest responsive bidder on a $2 million dollar public works project…
The firm’s client was the second low bidder on a roughly $29 million dollar public works project. The firm filed…
The firm’s client was the lowest responsive bidder on a multi-million dollar public works project. The second low bidder filed…
The firm successfully represented a client which was the lowest responsive bidder on an $11 million dollar public works project…
The firm’s client was the lowest responsive bidder on a $13 million dollar public works project. The second low bidder…
The firm represented a mechanical subcontractor with claims for work on a large private development in Palm Springs, California. The…
The firm’s client was the second-low bidder on a public works contract for the City of Pomona. However, the low…
The firm represented a general contractor in a dispute with a subcontractor on a public works construction project. Disputes arose…
The firm represented the general contractor on an airport improvement project. A surveyor was overheard referring to a project engineer…
The firm represented a design-build contractor in arbitration related to cost overruns and delays caused by the state’s failure to…
The firm represented a bridge-building subcontractor in litigation involving a CIDH pile contractor and the general contractor. The dispute centered…