Supplier Payment Claim on Public Project
The firm represented a material supplier in a claim for recovery of amounts due for materials it furnished to a…
The firm represented a material supplier in a claim for recovery of amounts due for materials it furnished to a…
The firm was retained by a multi-home developer to obtain a partial release of surety bonds securing a large subdivision…
The firm was engaged by a prominent specialty constructor with a mixed backlog of bonded and unbonded work to work…
The firm represented a retaining wall subcontractor in a dispute over wrongful termination of the subcontractor’s contract. Subcontractor sought payment…
The firm represented a construction manager who was wrongfully terminated from two school district projects and was owed substantial amounts…
The firm’s client was the second-low bidder on an Interstate 5 rehabilitation project (Engineer’s Estimate $38 million). The firm identified…
The firm was engaged pre-contract through project closeout to assist a key trade contractor with this unique government contract over…
The firm’s client experienced cost overruns and changed conditions on a northern California waste water treatment plant project. The firm…
The firm represented a subcontractor in a claim for recovery of subcontract balance and extra work performed on a publicly…
The Firm represented General Contractor in litigation contesting the Owner’s termination of General Contractor for cause on two separate contracts…
The Firm defended a performance bond, obtaining a dismissal of the client after filing a series of demurrers. A large…
The firm represented its client earth work contractor against a public water district in Northern California, in a claim for…