The firm represented a general engineering contractor in presenting and proving differing site condition claims related to a utility vault in the way of road improvements for a City project. The firm assisted the client in the delay and cost analysis. The firm then mediated a mid-project recovery and schedule reset —preventing the client from long-term financing of the City’s liability.