JBH Structural Concrete, Inc. v. Cleanline Concrete, Inc., et al.

The firm represented the structural concrete prime trade contractor in litigation arising from the construction of the expansion to the Larry D. Smith correctional facility. The firm initiated litigation against the place-and-finish subcontractor and the concrete supplier as a result of defective wall panels that had been constructed. The firm’s client alleged the wall panels were defective as a result of a combination of improper finishing and an incorrect concrete mix design. The case settled prior to trial for payment to the firm’s client.

San Diego Superior Court Case No. 37-2010-00084120-CU-BC-CTL

Counsel: Jason R. Thornton