Skip to content

General Contractor Prevails In Wind Energy Construction Dispute

The firm represented the general contractor in a dispute with a multi-national subcontractor over the construction of 100 wind turbine generators in central California.

The project was delayed – causing the general contractor to declare the subcontractor in default.  The subcontractor claimed over $8 million in additional construction costs due to changes, weather delays, impacts, and acceleration.  The subcontractor brought arbitration against the general contractor for the increased costs.

The firm’s first task was to evaluate the merits of the parties’ positions and determine whether the case could be settled.  Based on the firm’s recommendation, the general contractor made a seven-figure statutory offer to settle the dispute.  The subcontractor rejected the settlement offer.

Discovery results in critical insights.

Through discovery, the firm learned the subcontractor had not been properly licensed, had executed certain claim releases during construction, and had not incurred the claimed acceleration costs.  Discovery took multiple years, with twenty-four depositions across the country and in Canada.  The matter proceeded to a three-week arbitration at which eighteen witnesses were called.  During arbitration, the firm successfully rebutted the subcontractor’s excessive and inflated claims.

Firm and client prevail in arbitration.

Following arbitration, the subcontractor was awarded a small percentage of its overall claim.  Most importantly, the amount awarded to the subcontractor was less than the settlement amount offered by the general contractor years before.  As a result, the arbitrator ruled the firm’s client was the prevailing party in the matter, and that the firm’s client was entitled to its attorneys’ fees and costs to defend against the claim.

In the end, the firm’s client paid nothing to the subcontractor — a result significantly better for the firm’s client than had it accepted any of the multiple settlement offers made by the subcontractor.

Counsel: P. Randolph Finch Jr., Daniel P. Scholz, and Lindsey C. Herzik

Back To Top