The firm represented a subcontractor who had its subcontract terminated for convenience when it was roughly 65 percent complete with its work and had several requests for equitable adjustment and time extension requests totaling roughly a year of delay pending. The firm assisted the client with pricing and proving the claims, as well as termination pricing. After mediation, and follow on negotiation, the firm assisted the client with recovery of $35 million to resolve all disputes.
Counsel: P. Randolph Finch Jr. and Andrea L. Petray